The main types of shop drawings in construction follow the trades that fabricate and install the work: reinforcing steel, structural steel, precast concrete, millwork and cabinets, stairs and railings, curtain wall, MEP systems, and fire protection. Each type has its own content, its own reviewers, and its own governing standards, so the right way to read, prepare, or review a shop drawing depends on which trade it belongs to.
This guide covers the types of shop drawings by trade, shows what separates a fabrication drawing from an erection or coordination drawing, and gives a method for working out which packages a project needs. It starts with a map of the whole field and then goes trade by trade.
Key Takeaways
- Shop drawings are grouped by trade, and each trade’s drawings answer a different fabrication or installation question.
- Fabrication, erection, and coordination drawings do different jobs, even inside one trade.
- AISC describes four steel drawing types: shop, erection, erection bracing, and embedment.
- Rebar drawings are called placing drawings, and a detailer produces them from the design details.
- Precast packages split into erection drawings and production drawings for each member.
- Sprinkler drawings are working plans checked against NFPA 13 and reviewed by the authority having jurisdiction.
What Separates One Type of Shop Drawing From Another
Construction shop drawing types can be sorted two ways: by trade, which says who makes the work, and by function, which says what question the drawing answers. A fabricator needs piece-level information to cut, bend, and weld. An installer needs locations, sequence, and connection details. A coordinator needs to see how several trades fit into the same space.
The trade sets the vocabulary. Steel detailers talk about piece marks and erection plans. Rebar detailers talk about bar lists and placing drawings. Millwork shops talk about elevations and joinery. A reviewer who does not speak the trade’s language will miss the questions that matter, which is why trade shop drawings are rarely reviewed well by someone checking only for neatness.
A single trade can also produce more than one type. A steel package, for example, contains several different kinds of sheet. Keep that overlap in mind as you read the sections below, because most examples of shop drawings turn out to be a family of drawings rather than one sheet.
Fabrication, Erection, and Coordination Drawings
The clearest model comes from structural steel. As described in Modern Steel Construction, the AISC Code of Standard Practice defines shop drawings as drawings of the individual shipping pieces to be produced in the fabrication shop. Erection drawings show the location and attachment of each piece in the field. Erection bracing drawings, prepared by the erector, cover sequence and temporary supports. Embedment drawings show the items installed to receive the steel.
That four-way split works as a model for any trade. Fabrication drawings tell the shop what to make. Installation drawings tell the field crew where it goes. Interface drawings tell earlier trades what to leave in place for it. Coordination drawings tell everyone how all of it fits together in the same space.
The type also decides who carries the risk. Under the AIA General Conditions as quoted in the same article, the architect’s review is limited to conformance with the information given and the design concept. It does not check the accuracy or completeness of dimensions and quantities, which remain the contractor’s responsibility. Knowing which type of drawing is in front of you tells you how much checking is still yours to do.
Types of Shop Drawings at a Glance
The table maps the main trade groups to what their drawings show and what to check first.
| Trade Group | What the Drawings Show | Check First |
| Reinforcing steel | Bar sizes, quantities, spacing, locations, and bending details | Bar sizes, spacing, and splices against the design details |
| Structural steel | Piece drawings, erection plans, embedment plans, and connections | Member sizes, piece marks, and connection details |
| Precast concrete | Erection drawings and production drawings for each member | Connections, lifting devices, and reinforcement |
| Millwork and cabinets | Plans, elevations, sections, joinery, and finishes | Field dimensions, materials, and hardware |
| Stairs and railings | Layout, stringers, treads, railings, and connections | Dimensions, attachment points, and code requirements |
| Curtain wall and facade | Elevations, sections, anchors, and glazing details | Attachment to structure and fit with adjacent work |
| MEP systems | Duct, pipe, conduit, and equipment layouts | Clearances and coordination between trades |
| Fire protection | Sprinkler layouts, riser details, and hydraulic calculations | Design area, pipe sizes, and hanger locations |
Each row is a family of drawings, not a single sheet, so treat the table as a starting map and not a complete list.
Concrete and Structural Trades
ACI’s guide to presenting reinforcing steel design details defines placing drawings as detailed drawings giving the quantity, size, dimensions, spacing, and locations needed to fabricate and install reinforcement. A detailer produces them from the design drawings and design details. In practice, rebar shop drawings arrive as placing plans, bar lists, and bending details, and a missed bar mark can mean a delivery that does not match the pour.
Steel splits into the four AISC types described above. Engineers describe the review of structural steel shop drawings as a sequence: compare the erection plans with the framing plans, check the embedment plans against the design drawings, then examine the piece drawings for member size, material, piece marks, connections, and openings for other trades.
Precast work adds another layer. A typical university master specification for structural precast asks for two groups of drawings. Erection drawings show dimensioned plans, elevations, sections, connection details, and erection sequence. Production drawings cover each member, including dimensions, finishes, reinforcement, cast-in hardware, lifting devices, estimated cambers, and weights. The same specification requires the drawings to be sealed by a professional engineer licensed in the project’s state, which makes precast shop drawings a heavy engineering submittal.
Architectural Trades: Millwork, Cabinets, and Stairs
Millwork is drawn from the finished space outward. The Architectural Woodwork Standards say shop drawings should show construction methods, exact material selections, finishes, attachment and joinery methods, and exact dimensions, and that they serve as fabrication instructions and a guide for other trades. That is what separates millwork shop drawings from a design-intent drawing: the sheet is the instruction the shop builds from.
Casework sits inside the same family. Cabinet shop drawings add plans, elevations, sections, and hardware details, and they depend on field-verified dimensions. The same standards describe four approval outcomes: Approved, Approved As Noted, Revise and Resubmit, and Rejected. Choosing Approved As Noted over Revise and Resubmit can save weeks when every change is clearly marked.
Stair shop drawings cover layout, stringers, treads, railings, and the connections to the structure, and code-related dimensions such as rise, run, and guard height are easy to get wrong. The wider category of architectural shop drawings takes in doors, custom metalwork, and other one-off details that are fabricated for the project instead of bought off a shelf.
Mechanical, Electrical, Plumbing, and Fire Protection
MEP shop drawings exist to answer one question: do the systems fit in the space they were given? Each trade draws its own layout, and a coordination pass overlays them to find clashes before anything is fabricated or installed.
The individual layouts are drawing types in their own right. HVAC shop drawings show duct layouts, equipment, and hangers. Plumbing shop drawings cover pipe routing, risers, and slopes. Electrical shop drawings include single-line diagrams, panel schedules, and device and conduit layouts.
Fire protection shop drawings work differently because they are working plans checked against a standard. The Tennessee State Fire Marshal’s Office, for example, publishes a list of what sprinkler working plans must show: contractor information, a plan of each floor, a building cross section, a riser schematic, hydraulic reference points that match the calculation sheets, a sprinkler legend, pipe sizes and lengths, hanger locations, and hydraulic calculations. Reviewers check the sheets against specific NFPA 13 sections.
Building Envelope and Model-Based Drawings
Curtain wall shop drawings deal with the envelope: elevations, sections, anchors to the structure, and glazing details. Contractors usually review the attachment points and how the system meets adjacent work, because the facade touches steel, slab edges, and finishes.
BIM shop drawings are a different kind of category. They describe a method more than a trade: drawings produced from a coordinated model and turned into the fabrication-ready sheets the trade needs. The finished sheet is still a steel, duct, or pipe drawing. What changes is where the geometry comes from.
When a model feeds the drawings, the review question shifts. Is the sheet consistent with the model it came from, and was the model coordinated first? A mismatch between the two is a revision-control problem, not a drafting one.
Who Prepares Each Type of Shop Drawing
The preparer changes by trade, and that affects both quality and coordination. In steel, the detailer prepares the shop and erection drawings, transferring information from the contract documents into accurate, complete drawings with the dimensional detail needed for field fit-up. In concrete reinforcing, ACI describes the detailer as the party that produces fabrication details and placing drawings from the design drawings and design details.
In architectural woodwork, the manufacturer prepares and submits the shop drawings, samples, and product data, while the contractor coordinates the manufacturer’s drawings with the work of all other trades. Mechanical, electrical, plumbing, and fire protection drawings usually come from the subcontractor installing the system. Knowing who holds the pen tells you who to call when a question comes up, and which party owns the answer.
Working Out Which Shop Drawings a Project Needs
A project rarely hands over a list of the drawing types it needs. A short routine builds one from the contract documents:
- Read the specification sections and list every one that calls for shop drawings or submittals.
- Group those items into trade packages.
- Confirm who prepares each package, such as a detailer, fabricator, or subcontractor.
- Note the standard or code each package must follow.
- Set the review order, so earlier trades are settled before dependent ones.
- Plan a coordination pass for packages that share space.
The fifth step matters most for schedule. Steel and embedment drawings usually have to settle before the trades that attach to them can release their own sheets.
What Every Type Has in Common
Despite the differences, most trade drawings share a core of information that reviewers look for first:
- A title block with project, sheet, date, and revision.
- References to the specification section and contract drawings.
- Dimensions, with field-verified conditions marked.
- Materials, finishes, and product data.
- Notes that flag any deviation from the contract documents.
- Space for the review stamp and disposition.
A consistent sheet layout across trades makes review faster, because the reviewer finds the same information in the same place on every package.
Common Mistakes With Trade Shop Drawings
A few errors show up across almost every trade:
- Reviewing a package without knowing which drawing type it contains.
- Treating a coordination drawing as a fabrication drawing.
- Releasing a trade package before the embedment or interface drawings settle.
- Skipping the field dimension check on custom millwork and stairs.
- Assuming the reviewer checked quantities, when the contractor remains responsible for them.
Each of these is cheap to prevent at the start of a package and expensive to repair once material is cut.
A Worked Example: A Four-Story Mixed-Use Building
Consider a four-story mixed-use building. The following is illustrative, and real projects vary. The contractor sorts the specifications into six packages: foundation reinforcing, structural steel, curtain wall, ground-floor millwork, MEP systems, and fire sprinklers.
Sequencing follows dependency, not the order of the list. Placing drawings and embedments go first, then steel, then curtain wall, which attaches to the steel. MEP layouts go through a coordination pass before the sprinkler working plans are finalized. Millwork sheets start early, because they depend on field dimensions and the shop needs lead time.
The reviewers differ too. The structural engineer reviews the reinforcing and steel, the architect reviews the curtain wall and millwork, the MEP engineer reviews the systems, and the sprinkler plans also go to the authority having jurisdiction. Seeing that map on day one prevents the common surprise of discovering a missing reviewer at submittal time.
Where Trade-Specific Drafting Support Fits
Several packages landing in the same month can overwhelm a drafting team. Virtual Construction Assistants (VCA) places remote shop drawing and AutoCAD technicians with construction teams, and a technician placed through VCA can provide trade-specific drafting services across more than one package. Which trades a given technician has worked in varies by person, so confirm that during the hiring conversation. Once placed, the technician works directly with the client team on priorities and standards.
Things to Know
- Identify the drawing type before starting a review, since each answers a different question.
- Reinforcing steel detail drawings are called placing drawings, and a detailer prepares them.
- A steel package can include shop, erection, erection bracing, and embedment drawings.
- Precast specifications often require engineer-sealed drawings, so check the spec section.
- Sprinkler working plans are checked against NFPA 13, so review against the published checklist.
- A reviewer’s approval does not replace the contractor’s check of dimensions and quantities.
Frequently Asked Questions
What are the main types of shop drawings in construction?
They are grouped by trade: reinforcing steel, structural steel, precast, millwork and cabinets, stairs, curtain wall, MEP, and fire protection.
Within each trade there can be several drawing types, such as fabrication, erection, and coordination drawings. The packages a project needs depend on which specification sections call for submittals.
What is the difference between shop drawings and erection drawings?
Shop drawings detail pieces for the fabrication shop, while erection drawings show where each piece goes and how it attaches in the field.
The AISC Code of Standard Practice uses these definitions for structural steel. Other trades use similar splits under different names, such as production drawings and erection drawings for precast.
What are rebar shop drawings called?
Reinforcing steel shop drawings are usually called placing drawings, supported by bar lists and bending details.
ACI defines placing drawings as detailed drawings giving the quantity, size, dimensions, spacing, and locations of reinforcement. A detailer prepares them from the design drawings and design details.
Who reviews shop drawings for each trade?
The design professional reviews most packages, and some, such as sprinkler working plans, also go to the authority having jurisdiction.
The contract and specifications set the reviewers, so check each section. A review checks conformance with the design concept and does not replace the contractor’s check of dimensions and quantities.
Do all trades need shop drawings?
No, only the items the specifications call for, which usually means custom-fabricated or site-specific work.
Standard products are often covered by product data and samples instead. Each specification section lists whether it needs shop drawings, product data, samples, or a combination.
Mapping Your Project’s Trade Packages Before Submittals Start
Before the first submittal log is built, sort the specification sections into trade packages and name the drawing types each one will produce. Where two packages share space or depend on one another, mark the pair.
That one-page map shows who prepares what, who reviews it, and the order in which sheets need to move, and it is the quickest way to see where the types of shop drawings overlap on your own job. If the list is longer than your drafting team can carry, bring the package list to a conversation with VCA.